Flexible Intermediate Bulk Container (FIBC) for the Transport of Dangerous Goods, U-Panel Type C.

Size: 89x89x120cm, Coated, UV-treated, Tare: 2.75kgs

Body fabric: 200+30g/m2, Denier: 2100D/ 1700D, Color: White

Four lifting loops, W7 x H30cm, Fabric Weight: 55g.m

Fulling spout: Dia40x50cm, Dischcarge Spout: Dia45x50cm


Test Basis: UN Recommendations on the Transport of Dangerous Goods


SWL: 1000kg    Packing Group: II    SF: 6:1


Test preparation: The samples (NO.1-6) should be filled to not less than 95% of its capacity and to its SWL with plastic granules and carpolites, and the load should be evenly distributed.

  1. Top Lift

    After the filled FIBCs was lifted by its lifting loops until clear of the floor,the load of 6 x SWL=6000kg(including the contents) was loaded to a flat plate placed on the top of the contents and maintained for 5 minutes. No. of test samples:NO.5 No damage to the FIBCs or its lifting devices which renders the FIBCs unsafe for transport or handling and no loss of contents. "UN recommendations on the transport of dangerous goods"18th edition 6.5.6.5

  2. Tear

    The filled FIBCs was placed on the ground, a 100 mm knife score, completely penetrating the wall of a wide face, was made at a 45" angle to the principal axis of the FIBCs, halfway between the bottom surface and the {op level of the contents. The FIBCs was subjected to a uniformly distributed superimposed load of 2 x SWL:2000kg and maintained for 5 minutes.. Afterremoval of the superimposed load, the FIBCs was lifted clear of the floor by it's lifting loops and maintained in that position for a period of five minutes. No. of test samples: NO.6
  3. Topple

    The filled FIBCs was toppled by its top on to a rigid, non-resilient, smooth, flat and horizontal surface from a height of 1.2m. No. of test samples: NO.3
  4. Righting

    The filled FIBCs, lying on its side, was lifted at a speed of at least 0.1 m/s to upright position, clear of the floor, by two lifting devices. No. of test samples: NO.4
  5. Drop

    The filled FIBCs was dropped by its base on to a rigid ,non-resilient, smooth, flat and horizontal surface from a height of 1.2m. No. of test samoles: NO.1
  6. Stacking 

    The filled FIBCs was placed on its base on level hard ground and subjected to a uniformly distributed superimposed test load of 1809kg and maintained for 24hours. No. of test samples: NO.2